OUR NEW HOUSE

One day of construction at a time

Basement slab

Basement slab

The pouring of the basement slab is somewhat of a milestone, as it means we are close to getting out of the ground and building up. The concrete team has been working for weeks to prep the basement floor for the slab pour.  The floor started out with just bare dirt, the interior wall footings,Read more about Basement slab[…]

Backfill

Backfill

The excavation contractor worked on a the back fill last week.  This is the filling in of the space between the outside of the basement walls and the top grade of the lot.  As complete, the waterproofing looks like this. At the bottom is the French drain tube.  First they drape a fabric down theRead more about Backfill[…]

Foundation footings – planning for future efficiency and conservation

Foundation footings – planning for future efficiency and conservation

I was surprised when I saw the extent to which they dug footings for the foundation. A quick review of the foundation plans shows that there are quite a few load bearing walls in the basement that require footings. We are still scrambling to nail down the details of all the plumbing that will needRead more about Foundation footings – planning for future efficiency and conservation[…]