OUR NEW HOUSE

One day of construction at a time

Backfill

Backfill

The excavation contractor worked on a the back fill last week.  This is the filling in of the space between the outside of the basement walls and the top grade of the lot.  As complete, the waterproofing looks like this. At the bottom is the French drain tube.  First they drape a fabric down theRead more about Backfill[…]

Foundation footings – planning for future efficiency and conservation

Foundation footings – planning for future efficiency and conservation

I was surprised when I saw the extent to which they dug footings for the foundation. A quick review of the foundation plans shows that there are quite a few load bearing walls in the basement that require footings. We are still scrambling to nail down the details of all the plumbing that will needRead more about Foundation footings – planning for future efficiency and conservation[…]

Big big rocks

Big big rocks

I talked about how many rocks we were uncovering during excavation of our basement.  In the last few days we’ve watched them tackle the really big ones, that the excavator can’t budge. Now that rock was a monster.  When we dug back, it not only exposed 10 feet of depth, but there were two veryRead more about Big big rocks[…]